Messrs Khanzada Muhammad Abdul Haq Khan Khattak and Company v. WAPDA

JudgmentSupreme Court JudgmentsSupreme Court of Pakistan

Messrs Khanzada Muhammad Abdul Haq Khan Khattak and Company v. WAPDA

1991 SCMR 1436

Court / Forum
Supreme Court of Pakistan
Date
1991
Case Number
—
Bench / Author
Bench as recorded in the cited source
Subjects
Corporate & Commercial Law
Legal Provisions
Contract Act, 1872, section 74

Summary

WAPDA awarded construction contracts to the appellant, who could not complete the work within the stipulated time. The contract provided for liquidated damages, so WAPDA deducted Rs. 508,000 from the appellant's bills; the suit failed before the civil court and the High Court. The Supreme Court upheld the deduction: contracting parties may fix a genuine pre-estimate of loss, and liquidated damages are not a penalty — but where the amount named is oppressive or highly penal, the court may refrain from granting it and determine the reasonable compensation itself. WAPDA had proved the breach through evidence at trial.

Holding / Status

WAPDA's deduction of liquidated damages was upheld; under section 74 the court awards reasonable compensation, not exceeding the sum named, and may reduce an oppressive stipulation.

Verified Source

Judgment as discussed in LUMS Law Journal, 'Liquidated Damages — Common Law versus Pakistan Law', 1991 SCMR 1436 (law report)
Open the named source ↗

This record is general legal information from the firm’s News, Judgments & Legislation section — not legal advice for a specific matter, and no indication of how any court will decide another case. For reliance in proceedings, read the full text and obtain a certified copy where required.

Related practice area: Corporate & Commercial Law

✆