Hitachi Limited and another v. Rupali Polyester and others
Hitachi Limited and another v. Rupali Polyester and others
1998 SCMR 1618
- Court / Forum
- Supreme Court of Pakistan
- Date
- 10 June 1998
- Case Number
- Civil Appeals Nos. 958 and 959 of 1994
- Bench / Author
- Ajmal Mian, C.J., Sh. Riaz Ahmed and Ch. Muhammad Arif, JJ.
- Subjects
- Corporate & Commercial Law · Civil Litigation
- Legal Provisions
- Arbitration Act 1940, Sections 5, 11, 12, 30 and 31 · Arbitration (Protocol and Convention) Act 1937, Section 9
Summary
Hitachi, a Japanese company, contracted to supply a plant to Rupali Polyester for erection at Sheikhupura under a contract governed by the law of Pakistan, with an ICC arbitration clause providing for arbitration in London if Hitachi was the defendant. Rupali claimed the plant was defective; an interim award was made in London, and Rupali applied to the Senior Civil Judge, Sheikhupura, for filing of the award and for removal of the arbitrators for bias.
Holding / Status
The award was domestic, not foreign, because the arbitration agreement was governed by the law of Pakistan; the 'seat theory' was preferred to delocalised arbitration, Pakistani courts retained jurisdiction over the award, and the arbitrators were rightly not removed.
Verified Source
Lexology, 'First-step analysis: arbitration in Pakistan' (1998 SCMR 1618); Scribd headnote, '1998 SCMR 1618' (bench, date, case numbers); Khalid Anwer, 'The Rupali Case and the Theory of Concurrent Jurisdiction' (1998 SCMR 1618)
Source held in the law report / official record named above; certified copies are obtained from the court where a matter requires them.
This record is general legal information from the firm’s News, Judgments & Legislation section — not legal advice for a specific matter, and no indication of how any court will decide another case. For reliance in proceedings, read the full text and obtain a certified copy where required.
Related practice area: Corporate & Commercial Law